Hydro Electric Power Plant on Energy Engineering related Questions and Answers


Question :   The magnitude of runoff as ordinates against the corresponding percentage of time as abscissa gives ________
1. Mass duration curve
2. Load duration curve
3. Power duration curve
4. Flow duration curve
Answer :   4 - Flow duration curve  